RCT for Principal Contractors in Ireland: What Must Happen Before a Subcontractor Is Paid?

A subcontractor has finished the agreed stage of work. The invoice has been checked, the amount has been approved and accounts is ready to make payment. It may seem as though only one task remains: add the payee to the bank run.

For a principal contractor operating Relevant Contracts Tax, there are important steps before that payment is released.

RCT is a withholding system used for certain payments in the construction, forestry and meat-processing sectors. The applicable rate may be 0%, 20% or 35%, but the principal contractor should not guess the rate or rely on the percentage used for a previous payment. Revenue issues a deduction authorisation for the specific notified payment.

Here is how the process fits together.

First, Confirm the Working Relationship

RCT applies to relevant contracts with subcontractors. It is not a substitute for deciding if a worker is genuinely self-employed or should be treated as an employee.

That distinction deserves attention at the outset. Calling somebody a subcontractor on an invoice does not settle the matter by itself. The real working arrangement, including control, personal service and the nature of the relationship, needs to support that status.

Once the business is satisfied that it is entering a relevant contract with a subcontractor, it should collect the correct identifying information. This normally includes the subcontractor’s registered name, Tax Reference Number and documentary evidence of identity.

Trying to obtain these details on payment day is asking for delay.

Notify the Contract

The principal contractor should notify Revenue after entering the relevant contract. Details can include the sector, type of work, project location, expected dates and estimated value.

This stage creates the proper link between the principal, the subcontractor and the work. Revenue may issue a Site Identifier Number for the site or project, which is then used for contracts connected with that location.

Contract notification should be part of subcontractor onboarding. A practical business can build it into the same early process used to collect insurance documents, tax information, purchase orders and site credentials. Leaving RCT registration until the first invoice arrives compresses several tasks into the busiest possible moment.

Check the Approved Payment Information

Before submitting a payment notification, accounts needs a final figure and payment date. The gross amount supplied to Revenue must match the intended transaction.

This is where internal discipline matters. Draft invoices, disputed extras and unapproved variations should not drift into the payment list. The figure needs to pass through the company’s normal approval route first.

A useful payment record will identify:

  • the subcontractor being paid
  • the relevant contract or project
  • the approved gross payment amount
  • the planned payment date
  • the person who approved it

Clear records reduce the risk of notifying one amount and paying another.

Submit the Payment Notification Before Paying

The timing is central to the RCT process. Revenue must be notified of the gross amount and payment date before the principal contractor pays the subcontractor.

Once the payment notification is submitted through ROS, Revenue provides a deduction authorisation. This tells the principal contractor the amount of tax, if any, to withhold. It also confirms the gross payment, net payment and relevant deduction rate.

The principal should use the authorisation issued for that transaction. A subcontractor who had a 0% rate several months ago may not necessarily have the same rate today, since deduction rates can change with the person’s Revenue compliance position.

Follow the Deduction Authorisation

Suppose the approved gross payment is €4,000. A 0% authorisation means no RCT is withheld, so the net payment remains €4,000. At 20%, €800 is withheld and the net payment is €3,200. At 35%, €1,400 is withheld and the net payment is €2,600.

Those examples are simple arithmetic, but the principal’s decision must come from the actual authorisation rather than a manual assumption.

Where tax is deducted, the subcontractor should receive the relevant deduction details. This helps the subcontractor reconcile the payment and understand why the bank amount differs from the gross invoice value.

Review the Deduction Summary

Payment notification is not the final point in the cycle. Revenue produces a deduction summary after the monthly or quarterly return period. This lists the payments notified and the RCT due.

The principal contractor should review the summary for missing transactions or incorrect amounts. Once it is accurate, it becomes the return for that period. Tax withheld must then be paid to Revenue by the applicable deadline.

This review is easier when contract records, notifications, deduction authorisations and bank payments have been kept together. It becomes much harder when each item is stored in a different inbox or folder.

A Short Pre-Payment Check

Before releasing a subcontractor payment, accounts should be able to answer five questions:

  1. Has the relevant contract been notified?
  2. Is the subcontractor’s identifying information correct?
  3. Does the approved payment match the amount being notified?
  4. Has Revenue issued the deduction authorisation?
  5. Does the bank payment match the authorised net amount?

A “no” or “not sure” deserves attention before the money leaves the account.

Managed Support Can Remove the Weekly Rush

Some contractors handle every RCT task internally. Others use MyRCT to centralise contract registration, payment notifications and related payment administration instead of relying on scattered spreadsheets and email chains.

The right approach depends on volume, staff capacity and how often subcontractor payments are made. What matters is that the system works on an ordinary busy day, not just when the usual administrator is available and every invoice arrives on time.

RCT is manageable when each step has a place. Confirm the relationship, collect the details, notify the contract, notify the payment, follow the authorisation and check the return. Once that sequence becomes routine, subcontractor payments can move with far less uncertainty.